Dry Dock 5 (P-209) Construction Progress | November 2026
- Category
- Military affairs
- Source
- Officer in Charge of Construction Pearl Harbor Naval Shipyard
At a glance
- What
- Military Affairs
- Who
- Officer in Charge of Construction Pearl Harbor Naval Shipyard
- When
- Nov 26, 2026 at 12:16 AM UTC
Statement from Officer in Charge of Construction Pearl Harbor Naval Shipyard, November 26. Story by Jhewel Felipe.
JOINT BASE PEARL HARBOR-HICKAM, HAWAII โ The Officer in Charge of Construction Pearl Harbor Naval Shipyard (Oicc Phnsy) reports that crews placed more than 600 cubic yards of concrete in November for beams that will support the portal crane rails and foundations for the west electrical substation.
Crews continued to place more than 900 cubic yards of concrete at depths of 40 to 60 feet as part of construction on the main dry dock foundation. They also began installing ballast in the dry dock basin. The added weight will help hold the prefabricated floor units in place once dewatering begins.
Work also began on the water storage tanks for the dry dockโs Fresh Water Fire Pump House. Each completed tank will hold more than 80,000 gallons of usable water.