Statement from Fort Campbell Public Affairs Office, November 24. Story by Jedhel Somera.
FORT CAMPBELL, KY. โ Fort Campbell is midway through a $33 million infrastructure overhaul aimed at slashing utility costs and modernizing power systems across nearly 300 buildings without requiring upfront taxpayer funding. The installation is executing the upgrades through an Energy Savings Performance Contract managed by the U.S. Army Corp of Engineers, Huntsville, Alabama.
Under the third-party financing model, an outside energy services contractor pays for the initial construction and equipment, while Fort Campbell repays the balance over time using the money saved on monthly utility bills. Work began in December 2025 and is scheduled to wrap up by July 2027. Once completed, the contractor will maintain the systems for 22 years.
"We are not spending any money upfront, but we put about $7 million down that was received under other programs" said Mir Khan, a Fort Campbell Directorate of Public Works energy engineer and the local contracting officer's representative overseeing the project. If the upgrades fail to generate the projected energy savings, the contractor will only be paid based on the savings achieved.
Every dollar paid toward the contract is matched by guaranteed savings and reduction on installationโs electric demand and utility bills. "It is dollar for dollar, so whatever we spend, we will also save," said Elizabeth Parker, a DPW energy efficiency manager, explaining that the Army's repayments will never exceed the actual utility savings generated by the new equipment. The project targets barracks, administrative offices, warehouses and aircraft hangars, leaving Soldier and privatized on-post housing untouched.
Crews are upgrading interior and exterior lighting to LEDs in 289 buildings, installing automated climate controls in 52 buildings and replacing major heating and cooling units in two facilities. According to project officials, contractors have already completed roughly half of the lighting installations, finishing work in approximately 125 buildings. Beyond lowering electricity consumption, the brighter LED fixtures are improving visibility and workplace safety for Soldiers and DA civilians.
The high bays in motor pools and hangars have seen drastic improvement in lighting levels, improving the working conditions. Technicians are tying dozens of facilities into a central Utility Monitoring Control System. The network allows energy managers to remotely schedule the HVAC system based on the occupancy of a building and occupant comfort.
The HVAC systems are setback to unoccupied mode during non-working hours by coordinating with the building managers. The UMCS also helps to remotely switch the HVAC system during the changeover from cooling to heating or vice versa. The HVAC systems are remotely scheduled to come on for heating or cooling an hour before the occupied hours.
Buildings are placed in an unoccupied mode when units leave their headquarters for extended field exercises. "If a unit has training or operations happening for the next two weeks, it gives us the ability to go in and change those building schedules to accommodate the service members and their mission at hand," Parker said. The modernization effort also includes a $2.8 million boost to revive renewable energy infrastructure on post.
Local energy staff secured $2.8 million through the (REFoRM) Resilient Energy Funding for Readiness and Modernization program and folded the repairs into the current performance contract to bring the offline solar array back onto the installation's grid. As crews complete the efficiency upgrades, the installation qualifies for utility rebates and credits through TVA's EnergyRight program, which officials plan to apply directly toward paying down the project's financing balance.
For post leaders, the upgrades represent a long-term shift in how the installation manages power during peak demand while improving daily working conditions. "For barracks, we are improving quality of life of the Soldiers, and in the office areas, for the occupants," Khan said. "We're also creating safer work environments in barracks and the hangars."