Ribbon cutting marks completion of Chickamauga Lock upstream approach wall contract

Category
Military affairs
Source
U.S. Army Corps of Engineers, Nashville District
Military AffairsOfficial statement

At a glance

What
Military Affairs
Who
U.S. Army Corps of Engineers, Nashville District
When
Nov 17, 2026 at 12:58 AM UTC

Statement from U.S. Army Corps of Engineers, Nashville District, November 17. Story by Leon Roberts.

CHATTANOOGA, Tenn. (Nov. 16, 2026) - Project officials and regional leaders commemorated the completion of the Chickamauga Lock Upstream Approach Wall Contract today during an on-site ribbon-cutting ceremony. The upstream approach wall serves as a vital guide structure, steering commercial barges and recreational vessels safely into the lock chamber. The contract’s completion marks a critical step forward in delivering a modernized, resilient navigation facility designed to support regional commerce and national supply chains for decades to come.

U.S. Rep. Chuck Fleischmann (TN-03); Lt. Col. Guillermo Guandique, commander of the U.S. Army Corps of Engineers (USACE) Nashville District; and Doug McCrae, managing partner of C.J. Mahan Construction Company, LLC, delivered remarks on the project's significance before joining regional stakeholders atop the approach wall to cut the ribbon.

“This is a proud day for the entire project delivery team. Completing this contract represents the professionalism, persistence, and close interagency partnership required to advance an undertaking of this scale and complexity,” Guandique said. “Milestones like today’s completion matter because each one brings us closer to delivering a fully modernized lock, ensuring the long-term reliability and safety for commercial mariners and the recreating public.”

Guandique commended prime contractor C.J. Mahan Construction Company, project subcontractors, commercial dive teams, crane operators, and craft labor. He also lauded the Nashville District’s engineers, project managers, safety professionals, and quality assurance personnel for their on-site technical rigor.

Constructing the deep-water approach wall demanded intricate marine engineering under challenging river conditions. Crews anchored the foundation by drilling 14 eight-foot-diameter shafts through steel casings into bedrock up to 135 feet beneath the surface. Ready-mix concrete trucks staged on floating barges then placed thousands of cubic yards of underwater tremie concrete to secure the deep-water piers.

Setting the eight 420-ton pre-cast concrete beams for the superstructure required two heavy-lift derrick crane barges operating in tandem to hoist and position, each measuring 120 feet in length. Battling turbulent currents, commercial divers guided each nearly million-pound beam onto submerged bearing pads with pinpoint precision before crews bolted the assembly into a unified, impact-resistant guide wall. Supported across four intermediate piers and two nose piers, the completed structure will provide a continuous navigational guide along both sides of the channel.

According to McCrae, the U.S. Army Corps of Engineers gave the contractor three mandates: build a safe, high-quality project; deliver it on time; and complete it within budget.

“We’ve delivered on all three requests,” McCrae emphasized. “One in particular, though, I would like to highlight, and that’s our safety.”

Over the course of 1,856 days, crews logged more than 303,000 labor hours without a single lost-time injury - a remarkable benchmark for heavy marine construction.

“Accomplishing deep-water drilling, heavy tandem marine crane picks, and underwater diving directly adjacent to an active hydroelectric dam demanded exceptional skill,” said McCrae. “Delivering a structure of this scale and precision while upholding an uncompromised marine safety record makes this completion a proud engineering triumph. Milestones like this are only possible through disciplined execution, strong collaboration, and an unwavering daily commitment to safety.”

The milestone sets the stage for the final phase of the Chickamauga Lock Replacement Project at Tennessee River mile 471. USACE awarded the Approach Wall and Decommissioning Contract to C.J. Mahan Construction Company in February 2026. Under this final contract, crews will construct the downstream approach walls, breach the existing dam to connect the upstream approach to the new chamber, bring the new lock into service, and remove the temporary cofferdam.

Commercial river traffic will transition to the new facility during the decommissioning contract. Once operational, the new 600-by-100-foot lock chamber will accommodate nine jumbo barges in a single lockage - an 800% increase in efficiency compared to the single-barge capacity of the aging 1940 lock.

Fleischmann, a champion of Tennessee’s inland waterways and chairman of the House Energy and Water Appropriations Subcommittee, offered high praise for the skilled tradespeople on the front lines. He recognized the dedicated men and women who braved extreme cold and heat to deliver the work, hailing them as the true heroes of the project.

Fleischmann also commended the close partnership among the U.S. Army Corps of Engineers, C.J. Mahan Construction Company, and the Tennessee Valley Authority for bringing the milestone to fruition. “I look forward to being back with you all when we cut the final ribbon, and we bring nine barges at one time [through the new lock], as opposed to one through the existing lock,” Fleischmann said. “This will be an American success story.”

The U.S. Army Corps of Engineers Nashville District maintains and operates navigation locks, dams, and multi-purpose water resource projects across the Cumberland and Tennessee River basins, supporting flood risk management, commercial navigation, hydropower generation, environmental stewardship, and recreation.

The public can obtain news, updates and information from the U.S. Army Corps of Engineers Nashville District on the district’s website athttps://www.lrd.usace.army.mil/About/Districts/Nashville-District/, on Facebook athttp://www.facebook.com/nashvillecorpsand on X (formerly Twitter) athttp://www.x.com/nashvillecorps. Follow us on LinkedIn for the latest Nashville District employment and contracting opportunities athttps://www.linkedin.com/company/u-s-army-corps-of-engineers-nashville-district.

Source: U.S. Army Corps of Engineers, Nashville District

Understanding Global Threats

Browse All Topics & Pages

Complete sitemap with all intelligence resources

View Sitemap →

Related Preparedness Gear

Be prepared for evolving situations

Global Conflict Map

Live snapshot of conflict locations and tension zones worldwide.

Map data last updated: November 17, 2026

Related Alerts

Keep Exploring